Publication Date: 11/12/2024 Share Print

Previous Topic

Next Topic

Book Contents

Book Index

PN_EC_INSTDAYS - Count P/N E/Cs by E/C's Calendar Days or Part's Installed Days

Count P/N E/Cs by E/C's Calendar Days or Part's Installed Days

Affected Window: w_ac_planning_qry

eMRO- PNECINSTADAYS

logo_V5 small switch Note: In version 5 and later releases, the Calendar Days checkbox was changed to the Calendar Days drop down with the Yes, No, and No Fly options. With the No Fly option, Planning forecasts A/C E/C due dates based on calendar days starting from the A/C last flight date or E/Cs last compliance.

 

Formula

logo_V5 small switch The following is how Planning will calculate the P/N E/C Due Date with each switch setting.

Switch PN_EC_INSTDAYS set to Yes:

Calendar Days drop down options:

  • Yes - the planning forecast calculates the due date from the E/C's Effective Date.
  • No - the planning forecast calculates the due date from the part's installed date. For P/N E/Cs only.
  • No Fly - the planning forecast calculates the due date from the last A/C flight or last E/C compliance date, whichever is more recent. For A/C E/Cs only.

Switch PN_EC_INSTDAYS set to No:

Calendar Days drop down options:

  • Yes - the planning forecast calculates the due date from the E/C's Effective Date.
  • No Fly - the planning forecast calculates the due date from the last A/C flight or last E/C compliance date, whichever is more recent. For A/C E/Cs only.

logo_V4 small switch The following is how Planning will calculate the P/N E/C Due Date with each switch setting.

Switch PN_EC_INSTDAYS set to Yes:

  • Calendar Days checkbox NOT selected:
    • counts from last install date if it is later than the effective date;
    • otherwise, counts from last removal date if last removal is greater than effective date;
    • if none of the above applies, then it counts from the effective date.
  • Calendar Days checkbox IS selected:
    • counts from the effective date

Switch PN_EC_INSTDAYS set to No:

  • counts from last removal date if the last removal is greater than the effective date;
  • otherwise, it counts from the effective date.

Switch Set to Yes:

When set to Yes, in the Engineering Control, Schedule tab, three options are available from the Calendar Days drop down (Yes, No, No Fly) and the planning forecast calculates the E/C's due date based on the selection made. With this switch setting the Calendar Days drop down will default to No.

  • Yes - E/C due date is calculated based on Calendar Days starting from the E/C's Effective Date.
  • No - E/C due date is calculated from the parts installed date (if the installed date is after the E/C's Effective Date). For P/N E/Cs only.
  • No Fly - E/C Due Date is calculated from the last A/C flight or the last E/C compliance date, whichever is more recent. For A/C E/Cs only.

eMRO_Planning_Yes

Calendar Days drop down - No:

Notice that the following E/C has an Effective Date in 02/02/2017, a schedule with a 1000 days, and the Calendar Days drop down is set to No.

The following P/N is linked to the E/C (making it a P/N E/C).

The following serial number is linked to the P/N E/C but has not been complied with.

The P/N S/N was installed 09/09/2019.

Run a Planning Query for the P/N E/C. Because the Calendar Days checkbox is not selected, the Due Date for the P/N E/C is based on the part's Installed Date.

The Due Date is therefore 1000 days after the part's Install Date, 09/09/2019.

Note: If the part was installed on the aircraft prior to the P/N E/C's Effective Date, the planning forecast would count days only from the E/C's Effective Date, not from the part's installed date. For the planning forecast to include the days the part was installed on the aircraft prior to the P/N E/C's Effective Date, the user needs to determine the number of days accrued between the install date and E/C Effective Date and update the P/N E/C actuals for the part.

 

Calendar Days drop down - Yes:

Using the same P/N E/C above, the Calendar Days is set to Yes; the E/C Effective Date is still 02/02/2017.

Planning Query is then run for the P/N E/C. Because the P/N E/C's Calendar Days drop down is set to Yes, the planning forecast calculates the Due Date based on the P/N E/C's Effective Date.

The Due Date is therefore the particular number of Days after the E/C's Effective Date.

 

Calendar Days drop down - No Fly: logo_V5 small switch

An A/C E/C is created for an AD with a First and Repeat schedule of 10 days and No Fly is selected from the Calendar Days drop down.

eMRO Engineering Control, Schedule Tab v5

The A/C E/C Effective Date is 10/01/20.

Calendar Days - No Fly EC Effective Date

The A/C last flight date is 10/02/2020.

Calendar Days - No Fly AC Log Print 1

The A/C E/C is then complied with 10/13/2020.

Calendar Days - No Fly EC Compliance

The A/C EC Effective Date is updated to reflect the last compliance date.

Calendar Days - No Fly EC Effective Date_Comp_EFF_Date

Because the Calendar Days drop down is set to No Fly, when the planning forecast is generated it looks at the A/C last flight date and the E/C last compliance date (Effective Date) and uses the most recent date to calculate the Due Date. Since the E/C has not flown since 10/02/2020 and the A/C E/C was complied with 10/13/2020, the planning forecast uses the last compliance date to calculate the Due Date.

Calendar Days - No Fly Fleet Due List 1

The Due Date is therefore 10 days after the A/C E/C Effective Date.

PN_EC_INSTDAYS_12.5(18)

The A/C is then flown and the A/C last flight date is now 10/20/2020; the A/C E/C Effective Date is still 10/13/2020.

Calendar Days - No Fly AC Log Print 2

Because the A/C last flight date is more recent than the A/C E/C last compliance date, the planning forecast calculates the Due Date based on the A/C last flight date.

Calendar Days - No Fly Fleet Due List 2

The Due Date is therefore 10 days after the last A/C flight date, October 20, 2020

PN_EC_INSTDAYS_12.5(21)

 

Switch Set to No:

When set to No, only two options are available from the Calendar Days drop down (Yes, No Fly) and the planning forecast calculates the E/C's due date based on the selection made. With this switch setting the Calendar Days drop down will default to Yes.

  • Yes - E/C due date is calculated based on Calendar Days starting from the E/C's Effective Date.
  • No Fly - E/C Due Date is calculated from the last A/C flight or the last E/C compliance date, whichever is more recent (A/C E/Cs only).

eMRO_Planning_No

Note: When set to No, the mixed schedule functionality is activated. Therefore, if existing E/Cs accrue time while this switch is set to Yes and is later switched to No, utilizing a schedule of hours/cycles mixed with days will require you to contact Customer Support to review your data for optimal accuracy. This additional precaution is only required when switching from Yes to No settings. This precaution is not required for newly created E/Cs that have yet to accrue time/data.

In eMRO V5 (and later releases):
When PN_EC_INSTDAYS is set to No and Yes is selected from the Calendar Days drop down options, the system functions the same as when PN_EC_INSTDAYS is set to Yes and Yes is selected from the Calendar Days options - the planning forecast will use the E/C's Effective Date to calculate the due date. Refer to Calendar Days set to Yes example above.

When PN_EC_INSTDAYS is set to No, and No Fly is selected from the Calendar Days options, the system functions te same as when PN_EC_INSTDAYS is set to Yes and No Fly is selected from the Calendar Days options - the planning forecast calculates the due date from the last A/C flight or last E/C compliance date, whichever is more recent. Refer to the Calendar Days set to No Fly example above.

See Also

Planning Switches

ACPLANQ - Number of Lines When Planning Prints Summary is Exported As Excel

ACROLAVG - Use A/C Rolling Average for Mean Hours and Cycles

ALWMULTTSK - Prevent Element From Being Added to a Work Order

APUMEAN - Mean APU Calculation

AUTOMANHOURSSCHEDULE - Allow AUTO_MANHOUR_SCHEDULE_JOB to Appear in Trax Database Jobs

AUTOTSKPRIORITY - Enables The Setup Of Auto Prioritize Task For Planning

CPYSCHFROMTRANS - Use Planning Transaction Schedule for T/Cs on Work Orders with a Line Status

DUEATPRJCT - Project the Due At Hours and Cycles Using the Mean Hours and Cycles

EMPATTSEQ - Employee Attendance Sign-On / Sign-Off Next Sequence

FLSCHDAYS - Run Using Flight Schedule Days Config Number

GLBLDUEDATECALC - Run Mean Hours / Run on Flight Due Date Calculation

INTERACTPLANMANHOURS - Interactive Planner Displays Man Hours per Location/Site

LBRBYHCNT - System Labor by Head Count

LivePlan - Enables the Live Planning Functionality

MANHOURSAUTOCOMP - Auto Complete Certain Fields in Man Hours Schedule Override

MANPLNFLF - Default Man Hour Schedule Planner to Location/Site of the Employee

MELDEFLOC - Deferred Defect Convert Reported/Deferred Day to Local Time Zone

OVNDATADAYS - Define Number of Days to Display in Overnight Station Report Tab

OVNTACMS - Overnight Station Default

PASTASCH - Create Past Absence Record

PLANBY - Allows You to Set Planning to Weekly or Monthly

PLANDEPT - Planning Department and Planning Sub Department Fields Mandatory

PLANDUE% - Planning Warning When Percent Due

PLANPNSEQ - Planning P/N Next Sequence Number

PLNAUTO7D - Activate Seven Day Forecast Automatically at Set Interval

PLNHISTML - Determine Planning History Time Limit

PLNJBDFLT - Default Planning Job Checkbox

PLNJOBACNO - Run Planning Jobs by Program Instead of Oracle Scheduler

PLNJOBQUE - Activate Planning Job by Java Queue

PLNTRNNO - Planning Transactions Sequence Number Can Only Be Changed By The Application

SCHEDULEWORKG - Allow Work Group Selection Filter

SELFSCHLM - Self Assignment Schedule Date Range Limit

SHOPCAPNOT - Do Not Validate Against Shop Capability in the Shop Resource/Tasks Planner

SHOWDUEDT - Show Due Date Hours and Minutes

SHPPLNDLF - Default Shops Resource/Tasks Planner to the Location/Site in Employee Master

STREAMLINE - Clean Up Employee Schedules

TOEXITMS - Turn Off Exit Pop Up Message in Planning Query

TOOLWARN - Issues Warning If Tool Expires During W/O Scheduled Date Range

WOTCSCHDOVERWRITE - Overwrite existing W/O T/C Schedule Start/End Date with W/O Schedule Start/End Date

WOTRANSITCHECK - Automatic Transit Work Order Creation

YIELDCHECK - Validate W/O's Start Date is before E/C's Min Yield Date from Planning

Top of Page Publication Date: 11/12/2024 Share Print