Engineering Control, Other Tab

The Engineering Control, Other tab allows the user to enter additional information for an E/C.

engineering control other

 

The following information/options are available in this window:
_____________________________________________________________________________________

E/C Superseded By

The E/C entered in this field supersedes the original E/C selected into. This feature is used to phase in one E/C and phase out and terminate the current E/C selected. The E/C that is being superseded will be identified as such (flagged in red text) on the E/C General Tab.

E/C Superseded Date

The date that the superseding E/C takes effect.

Internal Capability checkbox

This checkbox indicates hat the work can be carried out internally as opposed to having a third party maintenance organization carry it out. This field is informational only.

Note: The Internal Capability checkbox is selected by default.

Do Not Include Child Man Hrs checkbox

When selected, the Man Hours calculation for Planning will not include the Man Hours for any Child E/Cs (Called On E/Cs). The checkbox also applies to the Work Order Man Hours in Planning. For additional information, refer to Man Hours, via A/C Planning Details of the Planning Training Manual.

MOD NO

Modification Numbers for E/Cs. This field is informational only.

Effectivity NO

This does not relate to A/C or E/C Effectivity. This field is informational only.

Ground Time Required

The amount of time needed for an aircraft to be on the ground in order to comply with the E/C. The time format is user defined by hours (0.00). This information appears on the A/C Planning Query results window as GTR (Ground Time Required). This field is mandatory when the Auto Reschedule checkbox is selected via the Engineering Control, Schedule Tab. For further information refer to the Auto Reschedule Functionality topic.

Inspection Program Reference

This field allows users to set a reference for all MPD tasks during the import process.

Expenditure

The G/L accounts linked to the expenditure code will be impacted when the E/C, and its associated Task Cards, are added to a Work Order. All materials issued, labor actuals, and expenses performed against this E/C impacts the expenditure codes financially. If the E/C does not have a defined expenditure code the system will use the W/O expenditure code to capture and record all financial impacts. Expenditure Codes are created via G/L Interface/ Update/ Journal Entries Expenditure. For more information, refer to the Configuring Expenditure Codes section of the G/L Interface manual. Financial transactions are recorded and available for review via the Journal Entries Query.

E/C Type

The Engineering Control Type.

E/C Check Type

This field allows the user to enter a system transaction code that sorts the Aircraft Check Status print contents based on the the configuration of the E/C Check Type transaction code. The Group/Sort Order field of the transaction code will sort E/Cs from shortest to longest check type based on their numeric value. For more information refer to E/C Check Type via the Engineering Transaction Codes Training Manual.

Note: This functionality is part of a customized print and is therefore not applicable for most users.

Associated Template logo_V7_small button

This field contains a selection of Templates that can be used in conjunction with the E/C.

FR (Fatigue Rate)

The Fatigue Rate being recorded by this E/C. This field is used to calculate fatigue schedules along with the Average Flight Time (AFT) and Basic Flight Time (AFB) parameters listed for specific Aircraft Type/Series. This functionality is used for Airbus aircraft only and should be provided by the manufacturer. For more information refer to Engineering Fatigue via the Engineering Training Manual.

FC (Fatigue Cycles)

The Fatigue Cycles being recorded by this E/C. This field is used to calculate Fatigue schedules along with the Average Flight Time (AFT) and Basic Flight Time (AFB) parameters listed for specific Aircraft Type/Series. This functionality is used for Airbus aircraft only and should be provided by the manufacturer. For more information refer to Engineering Fatigue via the Engineering Training Manual.

ETOPS checkbox

Indicates that this E/C is ETOPS rated with an extended range allotted to the aircraft.

EC Legacy

The legacy system's E/C name. This field functions as a mapping between a previous carrier's E/C name and the target carrier's E/C name. This field is not for manual input; it is populated automatically by an interface and is informational only.

but_Interface (gry) This field is part of a customized interface and is not available for all customers.

Capability Area

The Capability Area identifies where a maintenance task can be accomplished in association with the customer's internal capabilities (e.g., a particular E/C can only be accomplished during a heavy maintenance visit at a heavy maintenance capable Site). The Capability Area can be assigned for E/Cs, P/N Controls, and Defect Reports. However, a maintenance task with any Capability Area can be scheduled on Work Orders at Sites that have their Capability Area set to 'ALL'. For more information, refer to the Capability Area via the Planning Transaction Code Training Manual.

Maintenance Program

Maintenance Program enables the user to identify which Maintenance Program a particular E/C belongs to.

Planning Dept.

The Planning Department Code to assist the Planning department in filtering and planning tasks.

Note: When Switch PLANDEPT is set to Yes, the Planning Dept and Planning Sub Dept fields become mandatory in the following windows: P/N Control, Engineering Control/ Other tab, Defect Report/ Defer tab. When set to No, the Planning Dept and Planning Sub Dept fields are not mandatory. For more information, refer to Switch PLANDEPT via the Planning Switches Training Manual.

Planning Sub Dept.

The Planning Sub Department code to assist the Planning department in filtering and planning tasks.

Note: When Switch PLANDEPT is set to Yes, the Planning Dept and Planning Sub Dept fields become mandatory in the following windows: P/N Control, Engineering Control/ Other tab, Defect Report/ Defer tab. When set to No, the Planning Dept and Planning Sub Dept fields are not mandatory. For more information, refer to Switch PLANDEPT via the Planning Switches Training Manual.

Repair/Alteration

Defines if the record requires Repair or Alteration.

Other - The component is neither altered or repaired. This is a miscellaneous option.

Alteration - This compliance of the E/C will alter the component (i.e. the removal or addition of sub-components).

Repair - The compliance of the E/C will repair the component (i.e. a structural component has sheet metal work completed to strengthen the integrity of the structure).

None - Indicates that no repairs or alterations are required.

Repair/Alteration Classification

The level of Repair/Alteration (Major, Minor) required for this E/C.

Note: The Repair/Alteration Classification field is only visible if Repair or Alteration is selected in the Repair/Alteration field.

Repair Code

The repair code related to the E/C. For more information, refer to Repair Code via Order Transaction Codes Training Manual.

Weight and Balance checkbox

Select this checkbox to enter weight and balance information related to this E/C. When selected, the Weight On and Weight Off fields appear.

Weight On - The amount of weight added to the A/C once the E/C work has been accomplished.

Weight Off - The amount of weight removed from the A/C once the E/C work has been accomplished.

Suppress 'No Task Card' Message checkbox

Select this checkbox to suppress the following message from appearing when an E/C with no Task Card is added to a Work Order.

Note: Switch ADDECNOT must be set to Yes for the system to validate this checkbox. When ADDECNOT is set to No, regardless of the checkbox setting, an E/C that is not linked to a Task Card cannot be attached to a Work Order.

Electrical Load Change checkbox

Select this checkbox if E/C compliance will cause any changes to the power on the aircraft, due to electrical unit changes.

Note: This checkbox is for information only.

Next Controller E/C

Indicates that this E/C is a controller E/C. "Next" E/Cs that may be called on should not be scheduled until this controller E/C is complied with. This information appears in certain prints and planning queries and does not drive any functionality; it is only informational.

W/O Compliance Notification checkbox

Select this checkbox to have a system notification automatically sent whenever the E/C is complied with through the post completion of a work order. The user who the notification is sent to is configured through the Select Notification but_notification_small button to the right of the checkbox.

E/C Terminate Notification checkbox

Select this checkbox to send a notification to specific users informing them when the E/C has been terminated. This notification will contain detailed information regarding the E/C. To configure the notification select the Select Notification but_notification_small button to the right of this checkbox.

Config Affected Notification checkbox

Select this checkbox to send a notification to specific users informing them that the configuration was affected for this E/C once it is revised, released, and/or deleted. This notification will contain detailed information regarding the E/C. To configure the notification select the Select Notification but_notification_small button to the right of this checkbox.

Flt Ops Affected Notification checkbox

Select this checkbox to send a notification to specific users informing them that Flt Ops were affected for this E/C once it is revised, released, and/or deleted. This notification will contain detailed information regarding the E/C. To configure the notification select the Select Notification but_notification_small button to the right of this checkbox.

Warranty Affected Notification checkbox

Select this checkbox to send a notification to specific users informing them that the warranty was affected for this E/C once it is revised, released, and/or deleted. This notification will contain detailed information regarding the E/C. To configure the notification select the Select Notification but_notification_small button to the right of this checkbox.

Select Notification but_notification_small button

Select this button to configure the type of notification to be sent regarding any of the aforementioned appropriate checkboxes. When selected, the following System Notification window pops up. For more information, refer to Setup - System Notification via the Settings Training Manual.

_____________________________________________________________________________________

See Also

Engineering Control

Engineering Control, General Tab

Engineering Control, Schedule Tab

Engineering Control, Schedule Control Tab

Engineering Control, E/C Content Tab

Engineering Control, Optional Tab

Engineering Control, Software Tab

Engineering Control, P/N Effectivity Control Tab

Engineering Control, Warranty Tab

Engineering Control, Affected Manuals Tab

Engineering Control, Schedule Controlled By Tab

Engineering Control, Authorization History Tab

Engineering Control, Location/Site Ban Control Tab

Engineering Control, Restrictions Tab

Engineering Control, Informational Tab

Engineering Control, Revision History Tab

Engineering Control, Vendor Restrictions Tab

Engineering Control Buttons

Top of Page Publication Date: 11/12/2024 Share Print