Tool Forecast, via A/C Planning

The Tool Forecast merges the Planning element details (only W/Os) and the tool Spares Forecasting option from the Detail view.

Enter the desired search criteria then click the Find button. Inventory that corresponds with the search criteria will be displayed in the Results window.

AC Planning 4

AC Planning 5

 

Planning Elements:

The following information/options are available in this window:
_____________________________________________________________________________________

W/O checkbox

Select this checkbox to filter by Work Order.

Note: If this checkbox is selected, the system displays the W/O Location, Linked W/O Start Date Range, and W/O Schedule Start Date/Time Range fields in the Planning Filters section.

_____________________________________________________________________________________

 

Planning Actions:

The following information/options are available in this window:
_____________________________________________________________________________________

Elements checkbox

This checkbox has three different settings:

Plan Checked Elements - Will display tasks that have the Plan checkbox selected.

ALL Elements - Choose this option to query for Defects, E/Cs or P/N Controls that have their respective Plan checkbox either selected or not selected.

Plan Un-checked Elements - Choose this option to query for Defects, E/Cs or P/N Controls that have their respective Plan checkbox not selected. This cannot be selected by default.

Plan Element Due Date

The Planning query will only return planning element items that are due before the date entered in this field.

Within Hours/Cycles/Days

The Planning Query will only return maintenance events that have a Remaining Schedule that is less than or equal to the specified number of Hours/Cycles/Days.

And/Or drop down

Select 'And' to search for any Planning Elements which meet all search criteria. Select 'Or' to search for any Planning Elements which meet any search criteria. (i.e. Within Hours, Cycles and/or Days). Utilizing the 'Or' selection with the 'Within Days' functionality looks at the due date/current date, not just the remaining days of an E/C.

_____________________________________________________________________________________

 

From to Selection:

The following information/options are available in this window:
_____________________________________________________________________________________

From-To A/C

Enter the From-To aircraft tail number range for the forecast request. For additional information regarding Aircraft, please refer to the A/C Master, General Tab via the Settings Training Manual.

From-To A/C Type/Series

Enter the From-To aircraft type/series range for the forecast request. For additional information regarding A/C Type/Series, please refer to the A/C Type Series, General Tab via the Settings Training Manual.

From-To E/C Control

Enter the From-To E/C range for the forecast request. For additional information regarding the E/C Control, please refer to the Engineering Control, General Tab via the Engineering - E/C Training Manual.

From-To Chapter/Section

Enter the ATA Chapter/Section range for the forecast request. For additional information, refer to ATA Specifications via the Settings Training manual.

Customer

The Customer field allows users to search for results related to the selected Customers. This field is mapped to the Customers listed via the Settings/Update/A/C Master, Other 1 tab.

Select Customer select button button

Select this button to access a drop down selection of customers to select from and filter by. Select the Select All button to select all Customers. Select the Deselect All button to deselect all Customers. Click on the Select but_select_small button to select the marked Customer(s).

_____________________________________________________________________________________

 

Planning Filters:

The following information/options are available in this window:
_____________________________________________________________________________________

E/C Category

Enter the Engineering Control Category for the forecast request. For additional information regarding the E/C Category, refer to the eMRO Engineering Control, General Tab section of the Engineering - E/C Training manual.

Over Night Station

Over Night Station Code. For additional information regarding the Over Night Station, refer to the A/C Master, Optional 2 Tab via the Aircraft section in the Settings Training Manual.

E/C Status

Enter the Engineering Control Status for the forecast request. For additional information regarding these statuses refer to the Engineering Control, General Tab via the Engineering - E/C Training manual.

Planner

Select the Planner's name from the Employee Master. The Planner's name must be entered into the Planner field of the A/C Master, Optional 2 Tab. For more information regarding the Planner Field, refer to the A/C Master Optional 2 Tab via Aircraft Master section of the Settings Training Manual.

Capability Area

The Capability Area identifies where a maintenance task can be accomplished in association with the customer's internal capabilities (e.g., a particular E/C can only be accomplished during a heavy maintenance visit at a heavy maintenance capable Site). The Capability Area can be assigned for E/Cs, P/N Controls, and Defect Reports. However, a maintenance task with any Capability Area can be scheduled on Work Orders at Sites that have their Capability Area set to 'ALL'. For more information regarding the Capability Area, refer to the Capability Area section of the Planning Transaction Code Manual.

Planning Department

The Planning Department Code to assist the Planning department in filtering and planning tasks.

Note: When a code is entered into this field, the results for that specific code will be included in the planning query as well as results registered to department: 'ALL.' For example, if department 'HANGAR' is entered in this field, all E/Cs with department 'HANGAR' will be included in the query results along with all E/Cs with department 'ALL,' since an E/C that is related to 'ALL' departments is also related to department 'HANGAR.'

Note: When Switch PLANDEPT is set to Yes, the Planning Dept and Planning Sub Dept fields become mandatory in the following windows: P/N Control, Engineering Control/ Other tab, Defect Report/ Defer tab. When set to No, the Planning Dept and Planning Sub Dept fields are not mandatory. For more information, refer to Switch PLANDEPT via the Planning Switches Training Manual.

Planning Sub Department

The Planning Sub Department code to assist the Planning department in filtering and planning tasks.

Note: When a code is entered into this field, the results for that specific code will be included in the planning query as well as results registered to department: 'ALL.' For example, if department 'HANGAR' is entered in this field, all E/Cs with department 'HANGAR' will be included in the query results along with all E/Cs with department 'ALL,' since an E/C that is related to 'ALL' departments is also related to department 'HANGAR.'

Note: When Switch PLANDEPT is set to Yes, the Planning Dept and Planning Sub Dept fields become mandatory in the following windows: P/N Control, Engineering Control/ Other tab, Defect Report/ Defer tab. When set to No, the Planning Dept and Planning Sub Dept fields are not mandatory. For more information, refer to Switch PLANDEPT via the Planning Switches Training Manual.

Planned Location

This is used with the Planned section in the Planning Detail. Enter the Planned location. This is used in conjunction with the Planning Transaction button in the Planning results window.

Planned Start Date To

Planning section in the Planning Detail. This is used with the Work Order Planning Element. Enter the Planned Start Date (From-To range). This is used in conjunction with the Planning Transaction button in the Planning results window.

Modified Date (Range)

Enter the Modified Date (From - To) range of the Work Order for the forecast request.

Created Date (Range)

Enter the Creation Date (From - To) range of the Work Order for the forecast request.

_____________________________________________________________________________________

Enter the desired search criteria then click the Find button. Inventory that corresponds with the search criteria will be displayed in the Results window.

In This Section

Planning Results: Tool Forecast

See Also

A/C Planning Query

Part Forecast, via A/C Planning