RELEASE HANDBOOKS > eMRO Version 7 > eMRO 7.2 > Planning Control 7.2
Planning Control 7.2
|
|
Planning Control
|
|
Configurations Toolbar, via Planning Control
|
7.2
|
A/C Series - The aircraft series. When a Series is selected, all results in the Planning windows will be limited to that Aircraft Series.
|
|
Due List Window
|
7.2
|
Run Using Flight Schedule checkbox - The following functionality has been added:
Note: This field is controlled by Switch GLBLDUEDATECALC. For more information, refer to the Planning Switches module.
|
7.2
|
Run on Mean checkbox - When selected, the forecast will be based upon the mean hours/cycles.
Note: This field is controlled by Switch GLBLDUEDATECALC. For more information, refer to the Planning Switches module.
|
|
Interactive Planner Window
|
7.2
|
Run Using Flight Schedule checkbox - The following functionality has been added:
Note: This field is controlled by Switch GLBLDUEDATECALC. For more information, refer to the Planning Switches module.
|
7.2
|
Run on Mean checkbox - When selected, the forecast will be based upon the mean hours/cycles.
Note: This field is controlled by Switch GLBLDUEDATECALC. For more information, refer to the Planning Switches module.
|
7.2
|
Note: The system will consider all schedule parameters, including but not limited to, Flight Hours, Flight Cycles, and Flight Days when determining the overdue status of flight records and their associated E/Cs. An overdue flight record will be displayed as red with an accompanying clock icon.
|
|
Resources Window
|
7.2
|
Note: W/O records that occur on the same day display in a stacked format. Hovering the cursor on a record will display the W/O information.
|
7.2
|
Available MH - The following functionality has been added:
Note: Available man hours are displayed separate of Total Available Man Hours.
|
7.2
|
Skills drop down - Use this drop down to filter records based on the selected skill(s).
W/O drop down - Use this drop down to filter records based on the selected W/O(s).
|
7.2
|
Skill - The following functionality has been added:
Note: Remaining labor hours per skill are displayed in parenthesis next to their initial values.
|
Topic updated: 1/11/2024 7:28:26 AM
|