Publication Date: 11/12/2024 Share Print

Previous Topic

Next Topic

Book Contents

Book Index

Called On At, via Engineering Control, Schedule Control Tab

The Called On At control is used to specify when a child E/C will start a called on relationship to its parent E/C, and at what interval the child E/C will be called on afterwards.

The Start At field is used to specify at what parent E/C compliance (Completed NO) the child E/C is called on for the first time. The Frequency number determines the interval at which the child E/C continues to be called on to the parent E/C.

Note: When Switch MANLLOR is set to Yes, and the E/C is classified as Mandatory, the Lower Level and Ovr (override) checkboxes are disabled.

Note: This control may be utilized multiple times to set up an unlimited number of parent/child E/C relationships.

 

The following information/options are available in this window:
_____________________________________________________________________________________

Lower Level checkbox

When this checkbox is selected it indicates that all of the task card steps for the child E/C are contained within the parent E/Cs task card. When the parent E/C is added to a work order, the child E/C follows but any task cards related to the child E/C will not be attached to the work order.

Do not select this checkbox if the child E/C task cards are to be attached to the work order.

Ovr checkbox (Override checkbox)

This checkbox is not in use; it was designed for a specific customer.

Freq (Frequency)

The frequency number indicates the interval the child E/C is to be called on to the parent E/C. For example, if the frequency number is 2, every second time the parent E/C is added to a work order the child E/C will follow.

Note: If the Freq field is set to '0', the Called On At E/C will not track against the parent E/C after the Start At compliance has been made. If the Freq field is set to '1', the Called On E/C will follow at every occurrence of the parent E/C after the Start At compliance has been made.

Start At

The Start At number indicates at which parent E/C compliance (Completed NO) the child E/C should be called on to receive compliance.

With the Called On At control, if the Start At number entered is less than the actual Completed NO of the parent E/C, the parent/child relationship will commence at the next occurrence of the parent E/C.

E/C Called On Schedule Exceptions but_ec_called_on_schedule_exceptions_small button

Indicates that there are differences between the child E/C and parent E/C schedules. When the button is selected the system displays the E/C Called On Schedule Exceptions popup window displaying the fields where the schedule values are different.

_____________________________________________________________________________________

 

Called On At example:

Using the above parent/child E/C relationship, the child E/C should initially be called onto the parent E/C at the parent E/C's 3rd compliance (Start At = 3). The child E/C would then be called onto the parent E/C every second occurrence afterwards (Freq = 2).

The parent E/C has been complied with 2 times for A/C 901.

eMRO Called on At, Schedule Control Tab Example

The child E/C has not yet been complied with for A/C 901.

Upon the next compliance for the parent E/C the child E/C is called on.

The parent E/C has now been complied with 3 times for A/C 901.

And the child E/C, called onto the parent E/C's 3rd compliance, has also been complied with for A/C 901 and will now continue to be called onto the parent E/C every second occurrence.

When the parent E/C is complied with the 4th time, notice the child E/C will not be called on.

When the parent E/C is complied with the 5th time for A/C 901, notice the child E/C is called on.

And the child E/C receives its second compliance for A/C 901.

The child E/C will continue to be called on every second occurrence of the parent E/C.

See Also

Engineering Control, Schedule Control Tab

Called On, via Engineering Control, Schedule Control Tab

Called On 1st, via Engineering Control, Schedule Control Tab

Called On Repeat, via Engineering Control, Schedule Control Tab

E/C To Be Activated, via Engineering Control, Schedule Control Tab

E/C To Be Terminated, via Engineering Control, Schedule Control Tab

Terminated E/C if Terminated, via Engineering Control, Schedule Control Tab

E/C To Be Complied With, via Engineering Control, Schedule Control Tab

Top of Page Publication Date: 11/12/2024 Share Print