Called On 1st, via Engineering Control, Schedule Control Tab

The Called On 1st and Called On Repeat controls are meant to be used together, where an E/C is activated by one E/C (Called On 1st) and then repeated on another E/C (Called On Repeat).

When the Called On 1st control is used, the child E/C will be called on to the parent E/C one time only. The Start At field is used to identify at which parent E/C compliance (Completed NO.) the child E/C will be called on and complied with the parent E/C.

eMRO Called on 1st, Schedule Control Tab

 Note: This control can only be utilized once per E/C.

 

The following information/options are available in this window:
_____________________________________________________________________________________

Start At

The Start At number indicates at which parent E/C compliance (Completed NO) the child E/C should be called on to receive compliance.

With the Called On 1st control, if the Start At number entered exceeds the parent E/Cs current Completed NO then the child E/C will never get called on. For example, an E/C has been complied with against A/C 206 two times (Completed NO = 2), and the same E/C has been complied with against A/C 302 five times (Completed NO = 5). A parent/child Called On 1st relationship is then set up with Start At = 4. For A/C 206, since the Start At number is greater than the Completed NO the child E/C will be called on with when the parent E/C is at its 4 compliance. For A/C 302, since the Start At number is less then the Completed NO the child E/C will never be called on for this aircraft.

E/C Called On Schedule Exceptions but_ec_called_on_schedule_exceptions_small button

Indicates that there are differences between the child E/C and parent E/C schedules. When the button is selected the system displays the E/C Called On Schedule Exceptions popup window displaying the fields where the schedule values are different.

_____________________________________________________________________________________

 

Called On 1st example:

Using the above parent/child E/C relationship, the child E/C should be called on to the parent E/C at the parent E/C's 4th compliance, and at that time the child E/C will also be complied with.

The parent E/C has been complied with 3 times for A/C 901.

The child E/C has not yet been complied with for A/C 901.

Upon the parent E/C's 4th compliance the child E/C is called on.

The parent E/C receives its 4th compliance for A/C 901.

And the child E/C, called onto the prent E/C's 4th compliance, has also been complied with for A/C 901.

See Also

Engineering Control, Schedule Control Tab

Called On, via Engineering Control, Schedule Control Tab

Called On At, via Engineering Control, Schedule Control Tab

Called On Repeat, via Engineering Control, Schedule Control Tab

E/C To Be Activated, via Engineering Control, Schedule Control Tab

E/C To Be Terminated, via Engineering Control, Schedule Control Tab

Terminated E/C if Terminated, via Engineering Control, Schedule Control Tab

E/C To Be Complied With, via Engineering Control, Schedule Control Tab

Top of Page Publication Date: 11/12/2024 Share Print