eMRO v5 - Requisition Switches

REORLOC

When set to Yes, the system will take the total sum of quantities; on Requisitions and Quantity available at all Locations, and on all Orders from all Locations. If the sum is less than the Reorder Level quantity (defined in Settings/ Update/ P/N/ Inventory Levels Button), then the system will create a Requisition (using the P/N Requisition Window).

When set to No, the system will calculate the total sum per specific Location. If the sum is less than the Reorder Level for a specific Location, the system will create a Requisition for that specific location.